Interview with Germán Fañanás (LEF Ingenieros): NEXT-REVOS and the Utilization of Biogas Digestate | Eureka Eurostars
Biogas is expanding rapidly across Europe, but its growth brings a challenge: how can plants efficiently manage the increasing volumes of digestate they produce?
We spoke with Germán Fañanás, Manager at LEF Ingenieros, about NEXT-REVOS, a project adapting technology originally developed to concentrate desalination brines for use in the biogas sector. We explore its potential for plant operators, the results achieved through the Eureka Network’s Eurostars programme and the team’s experience throughout the funding process.
1. Germán, what is the LSRRO system and what led you to start this project?
Our starting point was a process we were already using in biogas plants to treat digestate: ultrafiltration followed by seawater reverse osmosis. We wanted to take the conversion of that reverse osmosis step further. We came across low salt rejection reverse osmosis through the Faculty of Chemistry at the University of Barcelona and quickly saw its potential: it allows us to increase conversion and obtain a much more concentrated reject stream, in other words, a product with greater value as a fertiliser.
2. What economic benefits can a biogas plant expect from adopting the LSRRO system?
It all comes down to concentration. With a three-stage LSRRO system, the reject stream reaches concentrations above the minimum levels set by Spanish Royal Decree 1009/2019 for digestates to be used as fertilisers. For the plant, that changes the equation: an effluent that used to represent a management cost becomes a product that can be applied to the land.
3. How has the consortium benefited from Eurostars funding, and what have you achieved so far?
So far, we have confirmed our expectations regarding both conversion and the stability of the system over time. These results have put us in a stronger position in the proposals we are presenting to biogas plant developers and builders. Now all that remains is for the construction of those plants to get under way.
4. How was your experience working with Evolution Europe throughout the funding process?

Our experience has been excellent. Information was always submitted to the Administration on time and in the correct format, and we have received every grant milestone payment on schedule. Whenever we had a question or query, the support we received was very good.